The Transmission Company of Nigeria (TCN) has reported that one of its critical infrastructures, the Shiroro-Katampe 330kV transmission line, has been vandalized, making the fifth such incident within February and March of this year.
A statement by Ndidi Mbah, GM, Public Affairs, said that at approximately 9am this morning, the Shiroro-Katampe transmission line experienced a trip.
According to the statement, “following initial investigations, TCN engineers attempted to restore operation but were unsuccessful.”
Adding: “Subsequently, efforts were made to identify the fault location. Hence, linesmen were dispatched to physically patrol the suspected area.”
The statement continued: “During the fault tracing process, vigilante team leaders in the vicinity notified TCN linesmen of vandalism along the Shiroro-Katampe transmission line. TCN personnel confirmed the vandalisation of the 330kV Shiroro-Katampe transmission line 1, from Towers 244 to 245, and the conductors stolen.”
The statement said “TCN is currently mobilizing for conductor replacement, pending completion of security operations at the site, saying that the second line remains fully operational, in conjunction with the Gwagwalada 330kV line serving the Kukwaba-Apo axis.
ALSO READ: Rumours Of Coup…
“Also, the wheeling capacity of TCN towards Abuja and environs would be enhanced by the Lokoja – Gwagwalada 330kV transmission line. TCN is working hard to minimise the adverse effect of these acts of sabotage on bulk power supply to Abuja and environs,” TCN said.
Furthermore, TCN said that this incident adds to a series of vandalism incidents recorded in February 2024, including the destruction of Tower 70 along the Gwagwalada-Katampe transmission line on February 26, 2024.
“Other incidents include the vandalism of towers 377 and 378 along the Gombe-Damaturu 330kV transmission line on February 23, 2024, and the attack on towers 145 to 149 and 201 to 218 along the Owerri-Ahoda 132kV transmission line on February 15, 2024. Additionally, on February 1, 2024, Tower number 388 along the Jos-Bauchi 132kV single circuit transmission line collapsed due to vandalism.”
TCN said that these acts of sabotage are unacceptable, and TCN urges relevant security agencies and host communities to collaborate in apprehending the perpetrators.
“Protection of the nation’s transmission paramount and collective efforts are required to curb these incidents,” TCN added.
TCN called upon all Nigerians to assist in reporting such acts of vandalism.
“Electricity infrastructure is a national asset, and safeguarding it is a collective responsibility,” the statement concluded.
-
News19 hours ago
Artificial Intelligence: DELSU Don Lists Benefits, Challenges For Media Houses
-
News18 hours ago
Wisike Files N1B Claim Against Ughelli North Council Boss, Egbo Over Alleged Defamation Of Character
-
Column18 hours ago
A Tale Of Two Videos By Sunny Awhefeada
-
Crime19 hours ago
Alleged N101.4 Billion Fraud: Court Orders Service Of Hearing Notice On Yahaya Bello
-
News6 hours ago
FG To Digitize Headquarters Of 774 LGAs By 2027